What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?

정답: A
What is the relationship depicted between Activity G and Activity H?

정답: D
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?

정답: C
Is activity 7001 pictured correctly in the precedence diagram?

정답: D
If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

정답: D
Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?

정답: A
The work breakdown structure is used to organize

정답: D
Determine the correct formula and date for the late finish for Activity 2002.

정답: B
Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

정답: C
Which of the following is NOT input data to the construction planning process?

정답: A