In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?
정답: C
Which of the following phases does NOT describe the commonly accepted construction life cycle?
정답: B
These are the activities on the critical path:
정답: D
What activities are concurrent to Activity 2001 in the "normal" schedule?
정답: C
If a detailed estimate is NOT available to assist in the formulation of activity durations but unit quantities have been identified, what information can be utilized to estimate work package/activity durations?
정답: D
For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.
정답: B
Which of the following is NOT required when performing weekly or monthly schedule updates?
정답: C
How much Total Float does drafting the product manual have?
정답: C
Time-scaled logic diagrams are
정답: A
Determine the correct formula and date for the late start for Activity 9001.
정답: B