A portfolio owner has asked to see milestone statuses for all projects in their portfolio. The report must filter out any complete projects. What steps should the project manager take to create this view?

정답: A
설명: (DumpTOP 회원만 볼 수 있음)
A stakeholder has identified a potential scheduling conflict on a current project. This conflict may affect the completion date by pushing it out two weeks. The stakeholder wants to document this timeline risk.
Which action should the stakeholder take to log the risk?

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
How would a project manager create a custom Workfront report to show information about issues logged to the projects they own?

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
A client has negotiated a discounted billing rate for video editing in a specific initiative.
How can the project manager override the default billing rate for the Video Editor within a project?

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
How would a project manager create a custom Workfront report to show information about issues logged to the projects they own?

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
Executive stakeholders require both current metric reports and a weekly recap on a project.
How can both needs be met?

정답: A
설명: (DumpTOP 회원만 볼 수 있음)
A company expects managers to complete a Workfront Business Case and submit it to the Project Sponsor for approval before a project enters Planning status.
What Workfront process will effectively facilitate the Project Sponsor review?

정답: C
설명: (DumpTOP 회원만 볼 수 있음)