최신 AgilePM-Practitioner 무료덤프 - APMG-International Agile Project Management (AgilePM) Practitioner
The Timebox to deliver the online reservation system through the Hoy Hall website has experienced a major issue. During Timebox C a test was completed to simulate an attack on the financial element of the online reservation system, with the intention of finding security weaknesses. It was found that it was potentially possible to gain access to the system, its functionality and data. Further work is therefore needed to meet the information security elements of a customer financial transaction.
Answer the following question about the actions to be taken by each role.
Column 1 describes a list of actions related to dealing with the security issue with the hotel reservation system.
Column 2 lists the key roles. For each action in Column 1,
select from Column 2 the role that should carry out the action.
Each selection from Column 2 can be used once, more than once or not at all.
Column 1
* Advise how the legislation on the transfer of data will affect the requirements and the system.
* Agree the changes needed to the corporate technical architecture with the Architecture Angels IT support team.
* Ensure the information security vulnerability is communicated to the AA Head Office IT Director.
* Evaluate the impact of proposed security controls on the business and decide on the most suitable solution.
* Reprioritise the requirements on the Prioritised Requirements List associated with the security issue.
Column 2
* Project Manager
* Business Sponsor
* Business Visionary
* Technical Coordinator
* Business Analyst
* Team Leader
* Business Ambassador
* Solution Developer
Answer the following question about the actions to be taken by each role.
Column 1 describes a list of actions related to dealing with the security issue with the hotel reservation system.
Column 2 lists the key roles. For each action in Column 1,
select from Column 2 the role that should carry out the action.
Each selection from Column 2 can be used once, more than once or not at all.
Column 1
* Advise how the legislation on the transfer of data will affect the requirements and the system.
* Agree the changes needed to the corporate technical architecture with the Architecture Angels IT support team.
* Ensure the information security vulnerability is communicated to the AA Head Office IT Director.
* Evaluate the impact of proposed security controls on the business and decide on the most suitable solution.
* Reprioritise the requirements on the Prioritised Requirements List associated with the security issue.
Column 2
* Project Manager
* Business Sponsor
* Business Visionary
* Technical Coordinator
* Business Analyst
* Team Leader
* Business Ambassador
* Solution Developer
정답:
Explanation:
* Advise how the legislation on the transfer of data will affect the requirements and the system.
* E. Business Analyst
* Agree the changes needed to the corporate technical architecture with the Architecture Angels IT support team.
* D. Technical Coordinator
* Ensure the information security vulnerability is communicated to the AA Head Office IT Director.
* A. Project Manager
* Evaluate the impact of proposed security controls on the business and decide on the most suitable solution.
* B. Business Sponsor
* Reprioritise the requirements on the Prioritised Requirements List associated with the security issue.
* C. Business Visionary
Rationale:
* A Business Analyst typically has the expertise to understand and communicate how data transfer legislation impacts system requirements.
* The Technical Coordinator is usually responsible for technical decisions, including those that impact the technical architecture, and would work closely with the IT support team to agree on changes.
* The Project Manager should ensure that key information, such as security vulnerabilities, is communicated to senior management, in this case, the IT Director.
* The Business Sponsor, who is ultimately responsible for the project from a business perspective, would evaluate the impact of security measures on the business.
* The Business Visionary is often tasked with understanding the strategic view of the project requirements and would be suited to reprioritize requirements, especially those with significant implications like security issues.
Which 2 statements represent appropriate entries for the Development
Approach Definition?
Approach Definition?
정답: C,D
설명: (DumpTOP 회원만 볼 수 있음)
Which 2 statements explain why the Timber Tigers' Site Manager would be an appropriate Solution Developer?
정답: B,E
The Close Out of Timebox B was completed as scheduled, but the Could Have requirement of tiled walls in the bathrooms was NOT delivered within this period, with the agreement of the team.
Which Agile principle MOST influences this course of action?
Which Agile principle MOST influences this course of action?
정답: B
Using the project timeline given in the Project Scenario, answer the following question about application of Timeboxing on the Hoy Hall project.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.
Assertion :
1. All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.
BECAUSE
The Investigation step within each Structured Timebox requires everyone working within the team to jointly agree how the requirements of the Timebox will be met.
2. Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off BECAUSE The aim of the Investigation step within each Timebox is to complete as much of the development work as possible.
3. It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.
BECAUSE
Each Timebox should comprise an Evolutionary Development phase and
Deployment phase.
4. It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.
BECAUSE
A typical Timebox Plan should provide a schedule of high-level activities for the imminent Project Increment.
5. It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.
Reason
BECAUSE
The Solution Development Team is responsible for planning the detail of all the work of each Timebox.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.
Assertion :
1. All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.
BECAUSE
The Investigation step within each Structured Timebox requires everyone working within the team to jointly agree how the requirements of the Timebox will be met.
2. Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off BECAUSE The aim of the Investigation step within each Timebox is to complete as much of the development work as possible.
3. It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.
BECAUSE
Each Timebox should comprise an Evolutionary Development phase and
Deployment phase.
4. It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.
BECAUSE
A typical Timebox Plan should provide a schedule of high-level activities for the imminent Project Increment.
5. It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.
Reason
BECAUSE
The Solution Development Team is responsible for planning the detail of all the work of each Timebox.
정답:
Explanation:
For each line, here is the appropriate option from A to E that applies:
* All internal works to be assigned to Timber Tigers throughout the project should be consolidated into one Structured Timebox.
* E. False (Assertion) False (Reason)
* Rationale: It is not practical or in line with Agile principles to consolidate all internal works into one Structured Timebox, as the work will likely need to be spread over multiple Timeboxes.
Additionally, the Investigation step involves agreeing on how to meet the requirements of the Timebox, not necessarily consolidating all work into one.
* Acceptance criteria for the front rooms to be developed in Timebox A should be described in detail and agreed during the Timebox Kick-Off
* B. True (Assertion) True (Reason) BUT the reason does not explain the assertion
* Rationale: While it is true that acceptance criteria should be agreed upon during the Timebox Kick-Off, the reason given is incorrect because the aim of the Investigation step is not necessarily to complete as much development work as possible but to plan and understand the work that will be carried out.
* It is appropriate that both the Evolutionary Development phase and Deployment phase are shown in the first Project Increment.
* A. True (Assertion) True (Reason) AND the reason explains the assertion
* Rationale: Each Timebox should indeed include both Evolutionary Development and a Deployment phase. This assertion and reason correctly align with the concept of Timeboxing in Agile.
* It is appropriate that the outputs of Timebox C are scheduled for deployment at the end of the first Project Increment.
* A. True (Assertion) True (Reason) AND the reason explains the assertion
* Rationale: The typical Timebox Plan does provide a schedule of high-level activities for the imminent Project Increment, which would include planning for deployment.
* It is appropriate that Earth Excavations create a detailed plan of activities they will complete during Timebox C.
* C. True (Assertion) False (Reason)
* Rationale: While it is true that Earth Excavations should create a detailed plan for their activities in Timebox C, the reason is incorrect as the Solution Development Team is not solely responsible for planning all work details within a Timebox. This task would typically be a collaborative effort involving all relevant parties.
An external web developer is to be contracted to create the new coffee bar insurance area on the existing web site. The chosen web developer will only agree to work on a 'fixed price for a fixed specification' contract.
What action should the Project Manager take?
What action should the Project Manager take?
정답: B
설명: (DumpTOP 회원만 볼 수 있음)
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
The objective of Solution Development Timebox B is to ensure that the front and east wings are finished and approved. The Project Manager has pointed out that acceptance criteria for this part of the solution need to be agreed.
Is this an appropriate action related to acceptance criteria?
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
The objective of Solution Development Timebox B is to ensure that the front and east wings are finished and approved. The Project Manager has pointed out that acceptance criteria for this part of the solution need to be agreed.
Is this an appropriate action related to acceptance criteria?
정답: B
설명: (DumpTOP 회원만 볼 수 있음)
The project is now in the second week of Timebox C. This is the final Timebox of Project Increment 1 and is scheduled to take one month. The plan is to open Hoy Hall to the public at the end of this Increment. A Must Have requirement of Timebox C is the implementation of a hotel reservation system.
At the Daily Stand-up, the Software Developer working on the reservation system reported that the framework for the system is now complete and ready for content.
However, this work cannot progress further due to a disagreement over the content. The Marketing Director insists the system is to hold professional photos and video tours of the facilities and grounds. These require a lot of storage space and regular updates. The IT Operations Manager insists the system is to take less than 5GB of storage space on the company server and require minimal maintenance.
The Team Leader has arranged a Facilitated Workshop to discuss the content and agree the way forward.
Remember to limit your answers to the number of selections requested in each question.
Which 2 individuals should the Facilitator invite to participate in the Workshop?
At the Daily Stand-up, the Software Developer working on the reservation system reported that the framework for the system is now complete and ready for content.
However, this work cannot progress further due to a disagreement over the content. The Marketing Director insists the system is to hold professional photos and video tours of the facilities and grounds. These require a lot of storage space and regular updates. The IT Operations Manager insists the system is to take less than 5GB of storage space on the company server and require minimal maintenance.
The Team Leader has arranged a Facilitated Workshop to discuss the content and agree the way forward.
Remember to limit your answers to the number of selections requested in each question.
Which 2 individuals should the Facilitator invite to participate in the Workshop?
정답: C,D
설명: (DumpTOP 회원만 볼 수 있음)