What is the purpose of tracking efficiency metrics for a formal review? [1]

정답: C
설명: (DumpTOP 회원만 볼 수 있음)
Testing Process
The following are the exit criteria described in the test plan of a software product:
EX1. The test suite for the product must ensure that at least each quality risk item is covered by at least one test case (a quality risk item can be covered by more test cases).
EX2. All test cases in the test suite must be run during the execution phase.
EX3. Defects are classified into two categories: "C" (critical defect) and "NC" (non-critical defect). No known C defects shall exist in the product at the end of the test execution phase.
Which of the following information is useless when the specified exit criteria is evaluated?
Number of correct responses: 1
K21 credit

정답: D
Defect Management
Consider a defect report and assume that a part of its lifecycle includes the following states:
New: Is the initial state
Working: Means that the developers are addressing the defect in order to produce a fix for the defect Clarification: Means that the developers need more information from the tester to address the defect and produce a fix for the defect and the tester is working to provide this information to the developers Verification: Means that a fix for the defect has been produced and the tester is running the adequate tests to verify whether the fix solves the defect Closed: is the final state Which of the following answers represents an invalid sequence of states that can't lead the bug report to the
"Closed" state?
Number of correct responses: 1
K21 credit

정답: B
What is the primary use for the traceability information regarding the relationship between test results and test conditions during test execution? [2]

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
When scheduling performance testing, which of the following approaches would be most advisable? [1]

정답: A
설명: (DumpTOP 회원만 볼 수 있음)
You are a Test Manager on a new project. The software that is being created will be used to control the projectors in movie theaters. This is a time critical project because the software must be released before the Christmas holiday season which has the highest movie attendance of the year.
You have decided to implement a review process for the work products that are a part of this release to save both time and money. In order to expedite the training, you brought in a consultant to train the participants and moderators in proper review processes. Your team is enthusiastic about participating in the reviews.
The project is in the early planning stages. As the review leader, what is an appropriate activity for you to be doing at this point in the project? [3]

정답: A
설명: (DumpTOP 회원만 볼 수 있음)
Test Management
Based on the historical data of 5 past and similar projects, you have calculated these average numbers of defects detected in system testing:
- for each 10000 LOC (lines of code), 200 defects
- for each person-month of development team effort, 49 defects
You want to use this information to perform estimation for a new project.
The project manager tells you that he/she has estimated 20000 new LOC for this new project.
Four developers work for four months on this project before system testing.
During system testing, 797 defects are discovered.
Assume that the system test of this new project is using the same amount of work as spent in the past projects.
Based on this information only, which of the following statement is certainly true about this project?
Number of correct responses: 1
K33 credits

정답: B
When closing out a defect report, which of the following developer commentaries is most likely to motivate a tester? [1]

정답: A
설명: (DumpTOP 회원만 볼 수 있음)
Test Management
Assume you have some data related to confirmation testing during system testing of a past project.
In that project 240 bug reports have been opened once, 80 were opened twice, 10 were opened three times and no bug reports have been opened more than three times.
You estimate that a bug report, which has failed its confirmation test, costs, on average, 3 person-hours.
Which of the following statements correctly describe the value of these confirmatory testing activities based on cost of quality?
Number of correct responses: 1
K32 credits

정답: A
You have written a defect report and have just been notified that it is in the "returned" state.
Who should take action on this defect? [1]

정답: A
설명: (DumpTOP 회원만 볼 수 있음)