최신 INTE 무료덤프 - ISM Supply Management Integration

A company moves its warehouse operations to a new location. Soon after, the company experiences higher shipping costs and delays in meeting delivery dates. Which of the following is the MOST likely cause of these increased costs and delays?

정답: C
설명: (DumpTOP 회원만 볼 수 있음)
During an inventory review, a supply manager confirms that parts used for the maintenance of equipment sold during the previous year are still being stored in the warehouse. These parts cannot be used on current equipment. Which of the following BEST describes these parts'

정답: A
설명: (DumpTOP 회원만 볼 수 있음)
A disaster response manager plans to deliver pallets of bottled water to volunteers at a disaster site. The water comes from a nearby bottling company at a preferential cost of $50 per pallet. The number of pallets of bottled water needed is impossible to know in advance due to numerous variables, although experience indicates that the likelihood of consumption is equal: a 25% chance each for 1, 2, 3 or 4 pallets of bottled water. If a full pallet is returned, a restocking fee of 520 is charged. If not enough water is brought in, the cost of purchasing a pallet of water on location is expected to be $200.
How many pallets should the manager deliver?

정답: A
설명: (DumpTOP 회원만 볼 수 있음)
FGH, Inc., a specialty construction company located in Italy, orders bulky customized sound equipment from a sole-source supplier in Asia. The equipment is to be installed in a new auditorium that FGH is constructing.
Failure to complete the project in time for its scheduled opening will subject FGH to penalties. FGH receives notice from the supplier that the equipment is packaged and ready to ship as planned via ocean freight but that an impending storm may cause delays. FGH needs to stay within budget. In this situation, which of following is the BEST course of action for FGH to take?

정답: C
설명: (DumpTOP 회원만 볼 수 있음)
A supplier of aircraft seating receives a forecast from a major aircraft manufacturer. The forecast information is considered confidential, and thus the supplier must sign a Non-Disclosure Agreement (NDA). Given this situation, which of the following is MOST likely to be protected by the NDA?

정답: C
설명: (DumpTOP 회원만 볼 수 있음)
A company that has never focused on supply management in the past is now faced with increasing competition from new, innovative products entering its market. As a result, the firm's business strategy includes an increased focus on cost containment. Given this situation, which of the following should the company do FIRST?

정답: D
설명: (DumpTOP 회원만 볼 수 있음)
Which of the following will be MOST useful for measuring service quality?

정답: C
설명: (DumpTOP 회원만 볼 수 있음)
A firm completes its near level production, five-month demand plan for the next business planning cycle:
Month 1Month 2Month 3Month 4Month 5
Demand Forecast15,00020,00025,00025,00018,000
Production Plan (Regular Time)20,00020,00020,00020,00018,000
Production Plan (Overtime)5,000
Ending Inventory5,0005,000
Average Inventory2,5005,0002,500
Workforce PlanningStarting WorkforceMonth 1Month 2Month 3Month 4Month 5 Hires7 Layoffs2 Actual Workforce Size132020202018 Regular Time Hours Required2,0002,0002,0002,0001,800 Overtime Hours Required500 Costs Regular time cost per unit$15 Overtime cost per unitS25 Monthly inventory cost per unit$1 Cost of hire$1,500 Cost of layoffS400 What is the cost of this demand plan?

정답: D
설명: (DumpTOP 회원만 볼 수 있음)
A large retailer and one of its suppliers establish a process to combine intelligence from both organizations in order to improve product availability while reducing inventory, transportation, and logistics costs. This process is known as which of the following?

정답: C
설명: (DumpTOP 회원만 볼 수 있음)
A manufacturer must work to reduce cost of goods sold (COGS) to achieve profit objectives and remain competitive in a tight market. The manufacturer has long standing relationships with its main suppliers and a strong supply management department that conducts periodic reviews with the suppliers. Nevertheless, the manufacturer is not hitting targets. Which of the following is the BEST course of action for supply management to undertake in order to initiate improvements?