You are a member of the audit team of a second-party audit of an organisation with 625 employees. The audit procedure recommends using sampling criteria which requires the review of the documented competence for
25 personnel. The audit team leader developed an audit plan allocating one hour to audit the Human Resources department (from 11:30 am to 12:30 pm). She told you that she could not allocate any additional time.
What would you do?

정답: D
설명: (DumpTOP 회원만 볼 수 있음)
Select six tasks you would expect to be completed at the audit team meeting of a third-party audit team leader and his audit team in preparation for a Closing meeting for a four-day initial certification audit.

정답: A,B,C,F,G,I
설명: (DumpTOP 회원만 볼 수 있음)
'XYZ' has already sent to you a list with all documented procedures and work instructions related to the services provided to 'ABC' (a quality manual is not included in the list).
To complete the audit planning which additional information would you ask to XYZ to submit? Select four.

정답: B,C,E,F
설명: (DumpTOP 회원만 볼 수 있음)
An organisation wants to certify their ISO 9001:2015-based QMS for the first time. Arrange the activities in the correct sequence from 2 to 5.
To complete the sequence, click on the blank section you want to complete so it is highlighted in red and then click on the applicable text from the options below. Alternatively, drag and drop the options to the appropriate blank section.
정답:

Explanation:
To certify an organization's ISO 9001:2015-based Quality Management System (QMS) for the first time, the correct sequence of activities would be:
* Establish the management system (already in place).
* Supplier audit
* Internal audit
* Management review
* Initial certification audit - stage 1
* Initial certification audit - stage 2 (already in place).
This sequence follows the typical path for preparing and ensuring that a QMS is functioning as required, leading up to certification.
An audit team leader arrives at a printing organisation to carry out a Stage 2 audit for a certification body. At a meeting with the Quality Manager, she is told that they have won their biggest contract from a computer manufacturer to print and compile computer documentation packages. They have leased the unit next door for space reasons but have never worked in this sector before. The Quality Manager wants the ISO 9001 certificate to cover the new contract.
Which one of the options is the correct response by the auditor?

정답: D
설명: (DumpTOP 회원만 볼 수 있음)
ABC is a fast food shop that receives orders by phone or the internet. The normal menu includes 15 different types of hamburgers; however, in the last two days, due to a shortage of a special type of meat, they can only prepare six of the 15 varieties.
You are performing a third-party audit of ABC; you observed that the menu offering food on the website is still the normal one, with 15 different hamburgers. During a 30-minute period, you observed several customers reluctantly accepting other than the hamburger they preferred. You decided to raise the following nonconformity as follows:
"There is evidence that ABC has not reviewed the ability to provide customers the offered products".
The restaurant manager does not accept the nonconformity. She says that ABC had an extensive training programme for all personnel, which you have already seen when auditing Human Resources. This shortage of some hamburgers cannot be considered a management system failure.
Which one would be your answer from the following options?

정답: D
설명: (DumpTOP 회원만 볼 수 있음)
A Health Trust has contracted with Servitup, a catering services company that has been certified to ISO
9001 for one year. It provides services to 10 small rural hospitals in remote locations involving the purchase and storage of dry goods and fresh produce, preparing meals and loading heated trolleys for ward service by hospital staff. You, as auditor, are conducting the first surveillance audit at one site with the Deputy Catering Manager (DCM).
DCM: "I apologise for the absence of the Catering Manager. He has called in sick today and we are really short of staff." You: "I see. It really shouldn't affect the QMS so the audit can progress as normal." DCM: "The Catering Manager set up the system. I'm afraid I'm not as familiar with it as he is." You: "OK, let's start with the Quality Policy. What are the main issues for the QMS here?" DCM: Give me a minute. I need to look at the Quality Policy on the noticeboard in his office.
You find that two internal audits have been carried out in the first year by the Catering Manager. One of them indicates that complaints from patients are increasing in number, mainly due to food being served too cold. The DCM comments that the trolley thermometer is often unreliable.
Which two of the following actions would be "correction" in dealing with the complaints?

정답: E,F
An audit team leader arrives at a printing company to carry out a Stage 2 audit for a certification body. At a meeting with the Quality Manager, she is told that they have won their biggest contract from a computer manufacturer to print and compile computer documentation packages. The Quality Manager wants the ISO
9001 certificate to cover the new contract.
During the audit, a team member found that some print jobs had been rejected by several clients over some months due to spelling errors in the print run. The Print Manager blames the new employees they had to take on because of a big contract.
The auditor finds that the responsibility for checking spelling errors is placed on the printer that sets up the print run.
In line with the policy of the certification body, the audit team raise improvement opportunities in the audit report. Which three of the following options would represent acceptable opportunities for improvement in the report?

정답: A,B,F
설명: (DumpTOP 회원만 볼 수 있음)
You are conducting a Stage 1 audit at an organisation that services refrigeration equipment for a large customer base.
The scope of certification is "Provision of refrigeration equipment maintenance and repair services". You are interviewing the Managing Director to learn more about the organisation and to explore how the requirements for policy, objectives, and risks and opportunities in ISO 9001 are addressed.
The Managing Director explains that they only use sub-contract refrigeration engineers and do not have any full-time refrigeration engineers, which helps to optimise overhead costs. The full-time staff employed are essentially a small team of office staff who process customer enquiries, schedule jobs and process invoices.
The Managing Director adds that the ISO 9001 requirements for competence of personnel extends to both sub- contract and full-time staff. He also states that the full-time staff are aware of the Quality Policy, objectives and plans to address risk and opportunities.
You ask if the sub-contract engineers have been informed of the Quality Policy, objectives and plans to address risks and opportunities, to which the Managing Director replies that this is not applicable as they only use sub- contractors who operate ISO 9001 certificated quality management systems. The documented information provided to the auditor confirms this.
Which clause in ISO 9001 is most likely not to have been fulfilled in this instance?

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
A small cleaning services organisation is about to start work on a hospital cleaning contract for the local Health Trust. You, as auditor, are conducting a Stage 2 audit to ISO 9001 and review the contract with the Service Manager. The contract requires that a cleaning plan is produced.
You: "How was the cleaning plan for the contract developed?"
Service Manager: "We have a basic template that covers the materials, labour requirements and cleaning methods to be employed. Some of that is specified by the customer." You: "How does the plan deal with locations like the intensive care wards and the operating theatres, which are included in the contract?" Service Manager: "The basic plan covers general wards, but we will do more frequent cleaning in those areas if the hospital requests it." You: "Are you aware of the regulatory requirements for cleaning standards in hospitals?" Service Manager: "No. We depend on the hospital to look after that side of things in the contract." You decide to raise a non-conformity against section 8.2.2.a.1 of ISO 9001.
You decide to raise another non-conformity against section 8.2.4 of ISO 9001 when finding that the cleaning plan was amended without the agreement of the Health Trust. A different cleaning chemical was substituted to that specified in the contract. At the follow-up audit, the corrective action proposed was to
"obtain a concession from the Health Trust for use of the new chemical." Which one of the following options is the reason why you did not accept this action taken?