최신 PMI-RMP 무료덤프 - PMI Risk Management Professional
A risk manager and relevant stakeholders have completed a risk response plan for a project. They have identified and planned responses to the known risks; however, a risk owner has identified and reported some residual risks not previously addressed.
What should the risk manager do first?
What should the risk manager do first?
정답: B
설명: (DumpTOP 회원만 볼 수 있음)
A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option's success is driven by multiple quantifiable factors.
What should the project manager do to evaluate and select the best option based on costs and probabilities?
What should the project manager do to evaluate and select the best option based on costs and probabilities?
정답: D
설명: (DumpTOP 회원만 볼 수 있음)
The project manager leading a company's digital signature initiative for engineering drawings has identified threats and opportunities using a strengths, weaknesses, opportunities, and threats (SWOT) analysis.
What are two potential threats or opportunities under the SWOT analysis? (Choose two.)
What are two potential threats or opportunities under the SWOT analysis? (Choose two.)
정답: A,D
설명: (DumpTOP 회원만 볼 수 있음)
A risk manager is preparing risk reports to be included in the monthly status report for project executives. How should the risk manager present the information?
정답: D
A new risk manager has been assigned to a delayed strategic project. The risk manager presented a new plan to get the project back on track using lessons learned and applying risk response strategies. Senior management wants to remove contingency reserves because they want to finish the project earlier.
What should the risk manager do in this scenario?
What should the risk manager do in this scenario?
정답: C
설명: (DumpTOP 회원만 볼 수 있음)
In a large industrial business, an on-going system development project faces a previously identified risk. The risk is adequately managed by the risk manager, however there is still residual risk.
What should the risk manager do?
What should the risk manager do?
정답: C
설명: (DumpTOP 회원만 볼 수 있음)
During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this particular risk should be mitigated to the greatest extent possible, however, the majority of other stakeholders feel that different risks have higher probabilities of occurring.
Which action should the risk manager take to address this risk?
Which action should the risk manager take to address this risk?
정답: C
설명: (DumpTOP 회원만 볼 수 있음)
During a project meeting, the project sponsor asks to close a project risk. The team does not recommend closing the risk because it is expected to be present in the next phase of the project work.
How should the risk manager address this concern?
How should the risk manager address this concern?
정답: A
The project risk manager is in the process of identifying risks. The project sponsor has communicated that there is an influential stakeholder who has a senior management position. The other stakeholders do not feel comfortable speaking in front of this stakeholder.
What should the project risk manager do next to identify risks?
What should the project risk manager do next to identify risks?
정답: C
설명: (DumpTOP 회원만 볼 수 있음)
A project manager is assigned to a new project and is told they need to develop the project's risk register. When should the project manager identify the project risks?
정답: C
설명: (DumpTOP 회원만 볼 수 있음)