A company has a project whose objective is to extract gold reserves from Field 1. However, another field closest to the company. Field 2, which has a higher probability of having twice as much gold reserves than Field 1. The risk manager requests the board of Directors to include Field 2 under the scope of the current project by management of change because the project's profitability will increase by 80%.
What type of request is the risk manager describing?

정답: C
A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing the risk manager should do?

정답: A
설명: (DumpTOP 회원만 볼 수 있음)
A project manager has determined that they cannot outsource work nor eliminate the scope. They also discover that they cannot buy insurance or mitigate the risk.
What should the project manager do?

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
Three months into a program, multiple workstreams are showing issues. At this point, the program manager requires that a risk impact assessment be conducted.
What will help calculate the impact?

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
The project manager has completed four projects all with similar scope. The project manager has recently been assigned to start on a new project and believes some risks may occur again on this project.
What should the project manager do?

정답: C
설명: (DumpTOP 회원만 볼 수 있음)
Which statement describes the risk portrayed on the risk matrix heat map below?

정답: C
설명: (DumpTOP 회원만 볼 수 있음)
A project team is concerned about a risk which, if occurs, might add additional complexity to their work. The team will need help from an external vendor, but the contracting process is long.
What should the risk manager do in this case?

정답: C
During a project progress meeting, a project team member is concerned that one of the risks has triggered several other low-level risks. These risks should be responded to quickly or there will be severe consequences for the project deliverables.
What should the risk manager do?

정답: D
In a large mobile network deployment project, there is delay risk due to insufficient staffing. The risk manager is considering executing a response plan, which involves allowing staff members to work overtime. However, this action may lead to excessive additional cost.
What should the risk manager do?

정답: B
A project team identified some risks in a project. Team members became interested in predicting the outcomes of their potential choices following their probability of occurrence.
Which technique should the risk manager use?

정답: B