Which theme provides the controls to escalate any forecast beyond tolerance to the next management level?
정답: B
Which is a purpose of the Controlling a Stage process?
정답: D
Which is a purpose of an End Stage Report?
정답: B
Which product identifies the management stages and timescales of a project?
정답: B
Which role is part of the Project Board?
정답: D
Identify the missing words in the following sentence.
The [ ? ] should include representation to satisfy the interests of the three primary categories of stakeholders affected by a PRINCE2 project.
The [ ? ] should include representation to satisfy the interests of the three primary categories of stakeholders affected by a PRINCE2 project.
정답: A
Identify the missing word in the following sentence, A project's output is produced during a project but the [?] for the project are often only realized after the project has closed.
정답: A
Which of the following statements about lines of authority and reporting are true?
1.The Project Manager has day-to-day control for a management stage within the limits laid,
2.If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.
1.The Project Manager has day-to-day control for a management stage within the limits laid,
2.If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager down by the Project Board.
정답: C
Which is a Benefits Review Plan used to assess?
정답: C
Which is NOT confirmed during the Initiating a Project process?
정답: A
Which may be funded from a risk budget?
정답: D
Which theme addresses the need to have a strategy for communicating with stakeholders?
정답: B
Which is a purpose of an Exception Plan?
정답: B