Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.

정답: C
설명: (DumpTOP 회원만 볼 수 있음)
Which is one of the three levels of plan in PRINCE2?

정답: A
설명: (DumpTOP 회원만 볼 수 있음)
What information about benefits management must be documented to meet the minimum requirements for applying the business case theme?

정답: C
설명: (DumpTOP 회원만 볼 수 있음)
Which is a benefit of using PRINCE2?

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
A new team member has joined the project team and wants to understand who else is on the project team, and who they report to.
Which management product should the team member review?

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
What theme estimates the cost of delivering the project?

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
Which is an objective of the Starting up a Project process?

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
Which is a purpose of the quality theme?

정답: A
설명: (DumpTOP 회원만 볼 수 있음)
Which is a purpose of the Risk theme?

정답: A
설명: (DumpTOP 회원만 볼 수 있음)
Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?

정답: C
설명: (DumpTOP 회원만 볼 수 있음)
Identify the missing words in the following sentence.
The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

정답: A
설명: (DumpTOP 회원만 볼 수 있음)