In which of these situations should the Scrum Team adjust their Work in Progress (WIP) Limits?

정답: A
설명: (DumpTOP 회원만 볼 수 있음)
True or False: Little's Law is used to forecast a Scrum Team's output.

정답: B
설명: (DumpTOP 회원만 볼 수 있음)
When using Kanban in a Scrum environment, some resistance toward introducing Work in Progress (WIP) Limits may be encountered. What is an alternative to introducing WIP Limits in Kanban?

정답: C
설명: (DumpTOP 회원만 볼 수 있음)
How does Kanban for Scrum Teams maximize value delivered?
(choose the best two answers)

정답: A,C
설명: (DumpTOP 회원만 볼 수 있음)
True or False: The primary effect of limiting Work in Progress (WIP) is that it creates a pull system.

정답: A
설명: (DumpTOP 회원만 볼 수 있음)
True or False: The Definition of Done still applies even if policies are explicitly stated at each column of your Workflow.

정답: A
설명: (DumpTOP 회원만 볼 수 있음)
What is the best chart to determine when a single item that has not been started will be finished?
(choose the best answer)

정답: D
설명: (DumpTOP 회원만 볼 수 있음)
Which metric makes most sense to look at during Sprint Planning?
(choose the best answer)

정답: B
설명: (DumpTOP 회원만 볼 수 있음)