최신 PSP 무료덤프 - ASIS Physical Security Professional
The linear scheduling velocity diagram has the following two-axis:
정답: B
Theoretically construct a summary activity for activities 2001 through 2004. Using the "normal" schedule, what is the cost of the hammock?
정답: A
Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?
정답: B
Using the crashed schedule, if you start Activity 2002 on 12 August 2021. what is the finish date for Activity
2002?
2002?
정답: B
How could the structural steel drawing delay have been prevented?
정답: A
What activities are concurrent to Activity 2001 in the "normal" schedule?
정답: C
Which of the following is NOT input data to the construction planning process?
정답: A
What is the workweek period for this project?
정답: D
An early start constraint dictates
정답: A
Considering the information provided for the project, what is the factor that most influences the successful crashing of the schedule?
정답: B