Company A acquires company B.
Which leads to a two-year program lo integrate the processes and systems Company B uses a different project management process, and the company's staff is unhappy about the acquisition As a result company B's project team fails to provide status and cost data in a format that conforms to the program standards.
What should the program manager do first?
Which leads to a two-year program lo integrate the processes and systems Company B uses a different project management process, and the company's staff is unhappy about the acquisition As a result company B's project team fails to provide status and cost data in a format that conforms to the program standards.
What should the program manager do first?
정답: B
A program manager prepares the program for review to secure funding by senior management. Which of the following must the program manager identify when creating the program charter?
정답: D
Exhibit:
In this future marina layout, what would be the pre-cabling guideline to follow for the terminal A?
In this future marina layout, what would be the pre-cabling guideline to follow for the terminal A?
정답: D
An ICT distribution designer is reviewing design documents with the owner to gam approval for an ER design.
Which of the following information about the site shall be included?
Which of the following information about the site shall be included?
정답: A
An organization must accelerate a product to market. The program manager completes the preliminary program slaps and holds a kick-off meeting Project managers submit their preliminary schedules for review What should the program manager do next?
정답: D
A software development program will launch iterative versions of new software called Alpha over two years Following that, a program will be released to the program team and developers to create new software called Beta While the program manager prepares the program closure plan tor Alpha, the program sponsor expresses concern about its support after program closure.
What should the program manager do as part of Alpha's program closure plan?
What should the program manager do as part of Alpha's program closure plan?
정답: D
You are designing distribution for a seven unit townhouse with in slab conduits. What is the MINIMUM number of 27 mm (1 in) rigid PVC Type 2 or metallic conduit that is required to satisfy distribution to each unit?
정답: A
When designing cable tray pathways under an access floor, what is the MINIMUM free space that should exist between the top of the cable tray side rails and the underside of the stringers?
정답: C
Which two of the following items should be considered for inclusion in a comprehensive working outline of a SoW? (Select two options.)
정답: B,E
What actions are taken in the process of developing and maintaining a program risk register?
정답: A
Using a vertical cable support structure can create issues for the cable attached to the pathway Several issues can result It the support work is not clone correctly. Which two of the following conditions could be caused by a poorly supported cabled (Select two options.)
정답: A,E
A global communications company's cloud-based platform will host its video network using both on - and off-shore learns. The program management office (PMO) assigns a program manager with little experience executing global initiatives.
What should the program manager do to resolve competing resource needs within components that could impact the entire program's overall delivery date?
What should the program manager do to resolve competing resource needs within components that could impact the entire program's overall delivery date?
정답: B
After new private equity owners acquire an enterprise, they want to improve its value by reducing costs A new program will restructure the enterprise, including an aging headquarters campus where the main data center is housed A strategic component project presents significant risk to organizational objectives due to Its complexity and dependencies on external parties. After a series of board meetings, the enterprise's investment committee approves a budget to Implement this component project, which will move the old data center from the aging headquarters campus into a new colocation facility Implementation of this component project may now begin, but is already one month behind schedule The program manager now perceives significantly more risk to the larger program due to this delay.
What should the program manager do to address this risk with the program sponsor and governance board?
What should the program manager do to address this risk with the program sponsor and governance board?
정답: A
Exhibit:
In this future marina layout, assuming that there are fewer than 10 slips being cabled, what would be the pre-cabling guideline to follow for terminal A?
In this future marina layout, assuming that there are fewer than 10 slips being cabled, what would be the pre-cabling guideline to follow for terminal A?
정답: D
Program A is dependent upon program B lo complete benefits sustainment for two benefits Program A is on track to meet program benefits However program B's program manager has just advised that program B has been closed.
What should program A's program manager update and review first with the stakeholders?
What should program A's program manager update and review first with the stakeholders?
정답: B
In which of the following design phases does the ICT distribution designer perform coordination with stakeholders and other disciplines (e.g.. mechanical, architectural, electrical) to ensure that the design is constructive and that any conflicts are resolved early in the process?
정답: C
When designing horizontal pathways, the ICT distribution designer should consider the design's ability to (Select two options.)
정답: A,B